# IMSERV delivers Capacity Market entry for Anglian Water

- Link: https://imserv.com/case-studies/imserv-delivers-capacity-market-entry-for-anglian-water/
- Published: 2019-05-01T16:55:07+00:00

Launched to ensure sufficient reliable electricity capacity is available, the Capacity
Market provides an opportunity for businesses to receive revenue by ensuring sufficient
generation or load capacity management to the grid at times of system stress. With
the market in its infancy, water company Anglian Water approached IMSERV to help
them ensure entry.

_“The Capacity Market has strict guidelines for market entry, and with a deadline
of only eight weeks to complete installation, we had to work quickly with Anglian
Water and Electricity Market Reform Settlement (EMRS) to determine the initial project
requirements before beginning our approach,”_ said Katrina Coombes, Bureau Manager
at IMSERV.

_“As Anglian Water was one of the forerunners in entering the Capacity Market, this
was a new and exciting challenge. It required all of IMSERV’s expertise and experience
to understand and execute the installation within a tight timeframe.”_

A bespoke Capacity Metering solution of 77 meters on back up on-site generation 
was installed, and IMSERV created the technical WP197 Metering Statements, which
passed the EMRS validation. By employing end-to-end project management and a consultative
approach, any issues that arose throughout the complex process were quickly resolved.

Katrina notes that the ground-breaking nature of the work nonetheless threw up challenges:_“
One aspect involved producing metering packs containing CT and metering certificates
as well as data from the installed meters – as there were no prior examples of these
packs available, we had to create a format that would achieve approval from EMRS.
To add to the pressure, the approval process took time, and with no possibility 
of extending the deadline there was little room for error.”_

Finally, Anglian Water and IMSERV attended a metering test and site audit with EMRS,
in order to ensure compliance with the EMRS guidelines. Subsequent audits have also
taken place since the approval, with a 100% success rate.

The result was Anglian Water securing entry into the Capacity Market, enabling it
to receive ongoing revenue from the scheme.

Tom Lee, Energy Contracts and Information Manager at Anglian Water, said: _“IMSERV
were quick to respond to our request for a quotation and tailored a service that
met our requirements. The short timescale was very challenging but IMSERV showed
excellent flexibility, depth of knowledge and expertise to enable us to successfully
obtain our Metering Test Certificate from EMRS.”_

Katrina credits the relationship between the two parties as crucial to the success
of the project. _“We worked closely with Anglian Water throughout the process, providing
technical support and regular updates whenever required,”_ she said, _“This communication
and teamwork was a key factor in achieving the outcome that both we and Anglian 
Water wanted.”_

Since the installation of the project, IMSERV has been delivering ongoing data collection
from the capacity meters, providing accurate data for settlement in the Capacity
Market to ensure accurate payments. The project is now being expanded to other energy
generation sources.